Applied Digital just signed the largest per-megawatt lease in its corporate history. The company disclosed Monday morning that an unnamed, investment-grade hyperscaler has committed to 150 megawatts of critical IT capacity over 18 years, generating about $5.4 billion in base-term contracted revenue. Run the math and you get roughly $2 million per megawatt per year, a rate that sits at or above the top of every comparable AI data center deal disclosed publicly in 2026. That number is not just a headline. It is a signal about where pricing power currently lives in the AI infrastructure stack, and what it means for everyone competing for capacity in a market where vacancy rates have collapsed.
One Deal That Pushes Applied Digital Past $41 Billion in Contracted Revenue
Applied Digital's November 23 press release describes the tenant only as a "Tier-One Investment-Grade Hyperscaler," a phrase the company uses to signal blue-chip creditworthiness without naming the customer. The lease covers 150 MW of critical IT load, begins delivering capacity in the first half of calendar 2028, and extends for 18 years as a base term. If the hyperscaler exercises every renewal option, the contract stretches to 33 years and generates about $12.7 billion in total revenue.
The deal pushes Applied Digital's total contracted base-term lease revenue above $41 billion, or about $100 billion if all renewal options across the entire portfolio are exercised. The company's contracted portfolio now spans more than 1.6 gigawatts of critical IT load across five campuses, backed by a grid-connected peak load capacity of 2.2 GW. Reuters reported that the announcement came on Monday and noted it follows a June 2026 deal at the company's Delta Forge 2 campus, a 15-year lease for 210 MW worth about $5.2 billion. The company's rapid lease buildout started with the Delta Forge 1 campus in April 2026, disclosed in an SEC Form 8-K as a 15-year commitment with a new investment-grade hyperscaler worth approximately $7.5 billion. That prior lease generated $5.2 billion over 15 years on 210 MW, working out to roughly $1.65 million per megawatt per year. The new lease, at approximately $2 million per megawatt per year, represents a clear step up in pricing power. Applied Digital's chief financial officer Saidal Mohmand stated the latest deal carries "improved commercial terms over our prior leases, including higher pricing." Applied Digital's stock surged about 13% on the news, according to Yahoo Finance, reflecting market confidence that the lease structure is fundable and the counterparty is credit-worthy.
Why the $2 Million Per Megawatt Price Is the Most Important Number in This Deal
The AI data center lease market in the United States has been moving fast, but disclosed pricing has clustered in a range that most analysts put at $1.2 million to $1.87 million per megawatt per year. Cipher Mining's lease with Amazon Web Services, announced in late 2025, covered 300 MW over 15 years for about $5.5 billion, implying roughly $1.22 million per megawatt per year. CoreWeave's lease at Applied Digital's own Polaris Forge 1 campus came in closer to $1.83 million. Independent rate analysis of the new Applied Digital deal puts the implied rate at approximately $2 million, above every figure in that peer group. The practical implication for hyperscalers is straightforward: securing a large block of AI data center capacity in 2026 now costs roughly 60% more per megawatt than it did in 2020, and the market shows no sign of correcting.
That premium does not reflect superior technology. Applied Digital builds purpose-built, power-dense AI data centers, but so do Equinix, QTS, Vantage Data Centers, and Digital Realty's xScale portfolio. The gap reflects scarcity. JLL reported that global data center absorption in the first half of 2026 hit a record 25 GW, more than the entire preceding five-year total. CBRE's North American data center market report confirms that vacancy rates are at all-time lows and asking rents have risen roughly 60% since 2020. When a hyperscaler is competing for a finite block of pre-permitted, pre-financed, investor-backed capacity, it pays a scarcity premium. Applied Digital's willingness to hold out for $2 million per megawatt proves the market will pay it. For comparison, Applied Digital's legacy data center hosting business in North Dakota runs at much lower economics, underscoring how dramatically the AI-focused colocation tier has repriced relative to general-purpose hosting in just three years.
The CBRE North America data center trends report notes that construction costs for hyperscale-ready AI campuses now run between $8 million and $14 million per megawatt for the shell alone, meaning Applied Digital is building assets worth $1.2 billion to $2.1 billion per 150 MW block before fit-out. At $2 million per megawatt per year in lease revenue, a fully occupied campus pays back its development cost in roughly six to ten years, leaving eight to twelve years of pure margin within the base term. That economics picture is why institutional capital like Macquarie is willing to fund construction before the first kilowatt-hour is delivered.
Three Candidates Behind the Mystery Hyperscaler and Why They Will Not Be Named
Applied Digital has not named the hyperscaler, and the press release gives no hints beyond "investment-grade." That secrecy is not unusual. Hyperscalers generally avoid disclosing their AI infrastructure buildout locations and partners because that information reveals where their capacity will be concentrated, what they are building toward, and when. A named tenant also invites regulators, competitors, and landlords to price future deals accordingly. The same logic is why AWS was not named in several large data center leases until 2025, when ownership structures forced disclosure in REIT filings. Applied Digital's existing named hyperscaler tenant at Polaris Forge 1 is CoreWeave, which signed leases for 100 MW and 150 MW at that campus. A second Tier-One placement that the company is not attributing to CoreWeave is likely one of the cloud majors.
The candidate list for a 150 MW deal commencing in H1 2028 is limited. Microsoft has committed publicly to spending $80 billion on AI infrastructure globally in fiscal 2026 and is one of the most active hyperscaler tenants in the third-party data center market. Google has been building out its own campuses but supplements with colocation for specific regions where in-house development timelines are too slow. Meta disclosed a multi-year buildout to reach 1.3 GW of AI compute by end of 2025 and continues expanding aggressively. All three are known to structure long-term leases with investment-grade covenants, which matches the press release description. Applied Digital's CEO Wes Cummins noted only that the deal "reinforces the strength of our customer relationships," implying a returning tenant rather than a new one. If the hyperscaler is new to Applied Digital, the CEO phrasing is odd. If they are a returning tenant, the choice narrows to two or three cloud majors.
How the Macquarie $5 Billion Equity Partnership Made These Lease Sizes Possible
Applied Digital could not absorb a $5.4 billion construction commitment from its own balance sheet. The company financed its earlier campuses with high-yield secured notes, issuing $2.15 billion in 6.750% Senior Secured Notes due 2031 and a subsequent $1.59 billion tranche at 7.000%, both through its APLD ComputeCo 3 subsidiary. That debt supports existing campuses but would not cover a new 150 MW build on its own. The capital structure that makes the new lease viable is the $5 billion programmatic equity partnership with Macquarie Asset Management, which the company disclosed earlier in 2026. Programmatic equity partnerships of this structure allow Applied Digital to draw capital campus by campus as construction milestones are hit, rather than raising a single large equity offering that would dilute existing shareholders immediately.
The Macquarie structure works as follows: Applied Digital develops a site and signs a lease, then draws on the Macquarie equity partnership as first-in capital before layering project financing backed by the lease cash flows on top. CFO Mohmand said the company expects to complete project financing for Delta Forge 1 and Polaris Forge 3 in Q1 2027 and for Delta Forge 2 in Q2 2027. The new 150 MW lease, with delivery in H1 2028, will follow a similar financing arc, with balance sheet equity first, Macquarie programmatic equity second, and project-level debt once the lease is in place. That structure lets Applied Digital commit to multi-billion-dollar capacity contracts without issuing massive amounts of new equity at dilutive prices. It is also why approximately 75% of the company's contracted base-term lease revenue now comes from investment-grade customers: institutional project finance lenders require that quality of counterparty before they will fund construction. The model is similar to how infrastructure REITs structure build-to-suit agreements, but without the REIT tax structure constraining the company's reinvestment flexibility.
The H1 2028 Delivery Date Hides Real Execution Risk
The bear case on this deal is straightforward: delivery in the first half of 2028 is conditional on "development milestones, utility arrangements and regulatory approvals" that are not yet in place. That language appears verbatim in both the press release and the Reuters wire, and it is load-bearing. AI data centers at this scale require dedicated utility substations, new transmission lines, and in many cases years-long interconnection queue positions. Applied Digital has not disclosed the location of this new 150 MW campus, which means it is impossible to assess from the outside whether the utility infrastructure exists or how far along interconnection proceedings are. Building a 150 MW AI campus requires roughly 200 MW or more of grid draw, accounting for cooling and power conversion overhead.
Skeptics point out that the data center construction pipeline across the United States is already showing strain. Discovery Alert's analysis of PJM's most recent capacity auction shows it cleared at the $325 per megawatt-day price cap and still came up 6,831 MW short of the reliability requirement for the 2028-2029 delivery year, with data center demand cited as the primary driver. Supply chain constraints for liquid cooling systems, transformers, and switchgear remain acute. Lead times for large power transformers in the United States now commonly run 18 to 24 months, meaning equipment orders for an H1 2028 delivery need to be placed no later than Q4 2026. If Applied Digital has not disclosed a construction location and equipment orders are not yet in progress, the H1 2028 date carries meaningful schedule risk. The company's stock, which surged 13% on the announcement, prices in smooth execution. Any slip toward late 2028 or early 2029 creates a gap in the projected revenue ramp that the market has not priced.
Three Dates Between Now and H1 2028 That Tell You Whether This Lease Closes on Time
Q1 2027 is the first meaningful signal. CFO Mohmand said Applied Digital expects to complete project financing for Delta Forge 1 and Polaris Forge 3 during that quarter. If those deals close cleanly, the institutional debt market is confirming that lenders are comfortable with Applied Digital's lease counterparties and construction execution record. A delay in those financings, or a financing that closes with tighter covenant terms than the company expects, would indicate that the market is pricing more risk into the pipeline than the November 23 announcement suggests. Project finance lenders have access to construction schedules, utility agreements, and due diligence that outside investors do not, making a successful close the most informative data point available on execution confidence.
Q2 2027 brings the Delta Forge 2 project financing. That deal covers the same 210 MW lease the company signed in June at $5.2 billion and is a leading indicator for how lenders will price the new 150 MW lease when it reaches the project finance stage. The third date to watch is a construction start announcement for the unnamed 150 MW campus. Applied Digital has not disclosed when that will occur, but for H1 2028 delivery at 150 MW scale, groundbreaking typically needs to happen 18 to 24 months in advance, meaning visible construction activity should begin no later than Q4 2026 or Q1 2027. A silence on campus location through Q1 2027 would be the clearest early warning that H1 2028 delivery is at risk. Applied Digital reports its next quarterly results in early 2027, and that call will be the company's first opportunity to give specifics on the new campus location, utility status, and construction timeline.
Applied Digital is now pricing AI data center capacity at $2 million per megawatt per year because scarcity, not technology, is the product it is actually selling.
Key Takeaways
- $5.4B, 18-year, 150 MW lease signed with an unnamed investment-grade hyperscaler, announced November 23, 2026, pushing total contracted base-term revenue above $41 billion
- Pricing is approximately $2 million per megawatt per year, above the $1.22M-$1.87M range of comparable disclosed AI data center leases and 36% above the company's June 2026 deal
- Total portfolio reaches 1.6 GW of contracted IT load across five campuses with $12.7 billion in total revenue available if all renewal options on this lease are exercised
- A $5 billion Macquarie Asset Management programmatic equity partnership funds construction as a first-in layer before project financing backed by lease cash flows follows
- H1 2028 delivery is conditional on utility arrangements and regulatory approvals not yet disclosed; Q1 2027 project financing closings for Delta Forge 1 and Polaris Forge 3 are the first execution signal
Questions Worth Asking
- If Applied Digital can command $2 million per megawatt per year while still financing construction with high-yield debt at 6.75-7%, what does that imply about how much pricing power the data center industry still has left to extract from hyperscalers?
- The hyperscaler's identity is undisclosed, but the lease term is 18 years starting in 2028. Which AI workloads require that long a commitment from companies that otherwise renegotiate nearly every contract in cloud computing?
- Applied Digital's portfolio is now concentrated in a handful of campuses funded through a single institutional equity partner. If Macquarie or the project financing market tightens, what is the company's fallback for the construction pipeline it has already committed to?